  • 25 December, 2022

    Very proud and thankfully of our teams that managed to carry out successfully 3 EFW Bunkers slipforms 24hrs working during November and December 2022.

    Skeleton Grange EFW in Leeds and Westfield EFW in Scotland started and completed exactly the same time 7th to 21st November.Each of them needing 15-25 steelfixers for each shift for 2 weeks requiring 100 extra steelfixers in total on top of other usual activities around each site. Big thank you to our supervisors, our clients that worked together with us and every operative involved in this major task to carry out these works in a such short time with highest standards on safety, quality and productivity.

    Kelvin EFW in Birmingham, Bunker slipform was done between 5th to 18th December on a very cold weather with temperatures between -5 to -10 degrees celsius each day. Thanks to our dedicated supervisors and all the teams on each shift that made this happen on such a difficult condition. Other thanks go to our client that decided to get hot water concrete from the supplier to unable to pour continuously 24hrs for 2 weeks
    on a such cold weather.

    Steelfixing works were done to highest standards on every aspect