    We are very proud to announce to have successfully delivered steel fixing work at the biggest slip form in Europe.  We would like to thank all our team for the hard work and long hours to complete this project. With the dedication and determination of our staff we made sure the project happened without any delay or issue. Please view the selection of our photos from the project below. 750t of steel have been fixed over continuous 10 days & nights 24-hour shifts.

    More information on the project please view here – http://multifuelenergy.com/fm2/