Latest

News

  • 21 December, 2023
    • BAE Systems, Glasgow
      Great progress at our BAE Project in Glasgow, thanks to our team, our  supervisors and our client that worked together with us to coordinate deliveries, have areas available to unable us to install for last 4 months 2350 tonnes of reinforcement and the overall scheme is well ahead on the program.
      Looking forward into 2024 as we are halfway through to continue at the same paste to meet all the requirements such as safety, quality and production at this major landmark project that will contribute to maintain future security of the United Kingdom.
    • Glasswater Locks, Birmingham
      Our scope of works is to complete the reinforcement to frame structures from the ground up to Blocks E1 – E4 8 floors each, in addition to the RC basement box to Blocks E1 – E3.
      There will be involved circa 2000 tonnes of reinforcement over a 54-week programme.
      Up to date 3 slipforms are complete with basement box and 3 floors at block E1.
      Looking forward into next year to maintain our high standards on safety, quality and productivity to meet all the requirements of our client and main contractor Berkeley Homes which are one of the highest in the industry.
    • Coop Live Arena, Manchester
      This scheme comprises of foundations, Core bases, complex capping beam, retaining walls, ground floor slabs, upper floors of the arena and roof. 1500 tonnes of reinforcement have been placed throughout the project up to date.
    • Lostock EFW, Northwich
      This scheme comprises of fifteen structures, including the waste bunker with slipform walls, boiler hall, turbine hall, tipping hall and associated buildings. 3200 tonnes of reinforcement have been placed throughout the project up to date.
    • SOYO, Leeds
      SOYO is the £300 million pound project creating a new neighbourhood at the heart of Leeds’ cultural quarter. The development is transforming the views along the Headrow within the city, and borders some of the city’s largest and most creative establishments including Leeds Playhouse, Leeds College of Music, BBC Studios and Northern Ballet. This scheme is done if different phases and we have been involved on all of them in the last 4 years. 3500 tonnes of reinforcement have been placed throughout the project up to date in structures such as foundations, slipform walls, PT and traditional slabs etc.